Two tools, built in parallel: an early design review for both sets the visual direction and briefs the designer — PDF templates, email templates, and the on-screen look of both tools — then everything converges on one joint walkthrough and one shared launch day.

Aug 25 Kickoff
Aug 28 Design review
Sep 15 Joint review — both tools
Sep 17 Both live in production

Both tracks at a glance

Each tool has its own lane below. The three pins crossing both lanes — design review, joint review, launch — aren't specific to either tool; they're shared moments for the whole project. Dates are business days only — the hatched seams mark each weekend, which is skipped, not worked.

IMPACT Gap Assessment First Fans First Design review — both tools Joint review — both tools Live in production Adjustment window Weekend (skipped)
TODAY
25Tue
26Wed
27Thu
28Fri
31Mon
1Tue
2Wed
3Thu
4Fri
7Mon
8Tue
9Wed
10Thu
11Fri
14Mon
15Tue
16Wed
17Thu
Design reviewAug 28
Joint reviewSep 15
Both liveSep 17
IMPACT Gap Assessment
KickoffAug 25
Design brief applied
Ready, holding for joint reviewSep 10
First Fans First
Build: backend + frontend + PDF (design brief incorporated)

Milestone by milestone

Same schedule, laid out as a list — useful for your calendar.

TueAug 25

Kickoff

Development starts on both tools at once — one team, two parallel tracks.

Done
FriAug 28

Design review — IMPACT Gap Assessment + First Fans First

A session with you covering both tools together, and the point where our designer gets the brief and material to start work — the PDF templates, the email templates, and the on-screen visual design for both.

Design
Tue–WedSep 1–2

Design brief applied & final checks

IMPACT Gap Assessment picks up the design direction, then a real end-to-end test.

IMPACT
Aug 28–Sep 9business days

First Fans First — in development

Backend, the four-step flow, and PDF/email delivery get built against the approved copy — with the design brief already built in. Weekends in between aren't worked.

FFF
TueSep 15

Joint review — IMPACT Gap Assessment + First Fans First

One call, both tools: the full functional walkthrough — PDFs and emails with the finished design applied — and the green light for launch.

Meeting
WedSep 16

Adjustments — both tools

Feedback from the joint review gets applied across both.

Both
ThuSep 17

Both tools go live — project complete

IMPACT Gap Assessment and First Fans First deploy the same day, linked from the site, and ready to collect submissions.

Launch